Featured image from the formal crane inspection for a 100,000-tonne anode-material manufacturing project.
Battery anode and carbon-based new-material plants need lifting equipment that can support production and maintenance while meeting strict project quality requirements. For procurement teams, supplier quality records, structural dimensions, wheel hardness, brake performance and non-destructive testing can be as important as the crane's basic capacity.
Henan Mine Crane manufactured a batch of cranes for Lanzhou Baohang's 100,000-tonne anode-material project. The source focuses on the project's A-level inspection carried out with experts from Baosteel Consulting and Shanghai Jinyi Testing.
The inspection team reviewed crane self-inspection records, material reports and non-destructive-testing reports. Physical checks included main-girder span, brake-wheel runout, wheel-tread hardness and crane travel mechanisms.
The source states that the inspected items were within the applicable standard range. For a buyer, this type of project demonstrates the importance of agreeing the inspection and acceptance plan before manufacturing is complete.
For the referenced battery-anode-material project, Henan Mine Crane supported a formal A-level inspection covering documentation and physical crane measurements.
Quality records included self-inspection, material certification and non-destructive-testing reports. Expert inspections included main-girder span, brake-wheel runout, wheel-tread hardness and travel mechanisms.
For a new procurement project, the same quality-control logic can be converted into an agreed inspection and test plan covering hold points, witness points, dimensional checks, electrical tests and final load testing.
| Recommended Solution | Project-Specific Overhead Crane Package for Anode Material Manufacturing |
| Referenced Project | 100,000 t/y battery anode / negative-electrode material project |
| Quality Documents | Self-inspection records + material reports + NDT reports |
| Factory Checks | Main-girder span + brake-wheel runout + wheel-tread hardness + travel mechanisms |
| Buyer Focus | Pre-shipment quality assurance and agreed acceptance criteria |
Detailed measurement and verification of crane machinery during factory acceptance. |
Surveying and dimensional verification of crane structures before project delivery. |
Acceptance team checking a key crane mechanical component against project requirements. |
Buyer and manufacturing teams jointly inspecting crane components and test results. |
Factory acceptance discussion between inspection experts and Henan Mine Crane project personnel. |
Crane bridge and trolley structures positioned in the factory for project inspection and verification. |
Project personnel inspecting trolley drive machinery and assembly details during FAT. |
Dimensional measurement of crane travel components during the battery-material project acceptance. |
Close measurement of crane wheel tread hardness as part of the formal acceptance program. |
Material reports and inspection records provide a quality trail for critical crane structures and components.
NDT reports can be included in the manufacturing documentation according to the project specification.
Main-girder span and other critical dimensions can be verified before delivery.
Brake-wheel runout and wheel-tread hardness are examples of project acceptance items.
Factory acceptance can be coordinated with external consultants or buyer-appointed inspectors.
| Battery Anode Material Plants | Production and maintenance lifting for negative-electrode material manufacturing. |
| Carbon-Based New Materials | Crane packages for graphite and carbon-material production. |
| Lithium Battery Material Projects | Industrial lifting equipment serving new-material process workshops. |
| Projects Requiring Formal FAT | Crane supply where third-party inspection and documented acceptance are required. |
Typical project documentation may include material certificates, welding and NDT records, dimensional inspection reports, component test records, electrical checks and load-test documentation, depending on the contract.
Yes. The referenced project involved external inspection experts, and inspection hold or witness points can be agreed in the quality plan.
Verify approved drawings, main dimensions, wheel and brake condition, mechanism operation, electrical functions, safety devices, documentation and any project-specific FAT criteria.
Send your load data, workshop layout, production process, environmental classification and control requirements. Henan Mine Crane engineers will review the application and prepare a project-specific crane proposal.